Forest Service Says 4FRI Is Still Alive

Forest Service Says 4FRI Is Still Alive

Following its cancellation of the Phase 2 Request for Proposal (RFP) and bid selection in September, which caught everybody by surprise, the Forest Service “has gone back to work” on how to move forward with stewardship and treatment of the 520,000 acres that was included in Phase 2, which was part of the 4 Forests Restoration Initiative (4FRI) seeking to improve forest health conditions on more than 2.5 million acres across four Arizona national forests while establishing wood products manufacturing and biomass processing infrastructure.

The agency hosted an industry roundtable of 4FRI stakeholders on October 12 in Heber, Ariz. that addressed restoration strategies and “lessons learned.”

“Our critical work will continue with the goal of increasing the pace and scale of forest restoration across the 4FRI landscape,” the agency said, adding that the cancellation of Phase 2 does not affect any ongoing forest restoration or fuels reduction work, including stewardship agreements in place and plans to issue new timber sales in 2022.

“It was a surprise for sure,” comments John Godfrey, principal of Godfrey Forest Products, after the FS cancelled the Phase 2 RFP, just when it appeared the agency was about to award the winning bid on the 20-year, 520,000 acres stewardship contract.

Godfrey’s bid, apparently one of two in serious contention, included the construction of an 850MMSF oriented strandboard plant in Winslow, Ariz. Godfrey has developed several OSB facilities through the years.

The Forest Service cited “performance risk” concerns as a reason for the cancellation. The Phase 2 contract award announcement had been delayed several times since 2019 due to 13 contract modifications including reductions in stewardship acreage from as high as 800,000 acres during initial discussions. Upon the cancellation, the FS stated, “The requirements for meeting the restoration objectives (as currently defined in the RFP) are not reasonably aligned to industry needs. In addition, significant financial and investment risks remain which ultimately represents a performance risk to the government.”

In so many words, over a 20-year period what happens if FS timberlands dedicated to the project are somehow made unavailable due to fire damage or administrative withdrawal? How does the FS replace those resources and how are Phase 2 investors to be placated or compensated?

The FS statement added, “It is in the best interest of the government to thoroughly reassess the requirement so that any new solicitation issued would better address all risks to offerors and the government, including financial and investment risks.”

Gofrey remains committed to the process. In addition to a site for the plant, Godfrey’s OSB project has completed an engineering design, preliminary air work, and he has a number of contractual relationships lined up.

“It’s a great place to build a mill,” he says. “It’s in the middle of a big market. It’s also meaningful to be part of forest restoration, fire reduction and preserving the water supply. There’s no reason to throw this away. If it takes another year then that’s what it takes.”

News of the cancellation brought outcries from several stakeholders, including politicians and others. Arizona Gov. Doug Ducey and other elected officials slammed the decision, citing the federal government’s inability to step up to address wildfire risks and protect Arizona communities.

The Phase 2 setback continues a tough run for the 4FRI effort: Phase 1, initially awarded in 2012 then transferred in 2013 to its current owner NewLife Forest Restoration, and including 300,000 acres over 10 years, has been hampered due to lack of logging and conversion capacity and is just now appearing to turn the corner on infrastructure needs while the number of acres actually treated remain well below initial projections.

NewLife, which is in the process of installing a sawmill at Bellemonte, Ariz., was apparently the other major bidder for the Phase 2 contract. There was some speculation that both Godfrey’s and NewLife’s bids would be partially or fully awarded.

A big sticking point in operating the Phase 1 contract (and the same for Phase 2) is a lack of biomass markets in the state, while the overall 4FRI will require producing mountains of the low-quality material. There’s only one dedicated biomass power producer in Arizona, Novo Power, which has utilizing material produced in ongoing forest health operations in the White Mountains area, but at 24 MW can only process so much.

Novo Power, operating at Snowflake, Ariz., participated in both the sawmill and OSB bids to take the biomass resulting from those two projects.

“I was stunned by the cancellation,” comments Novo Power President Brad Worsley. “I knew that there was always a possibility of cancellation but the stated reasons for cancellation were true a year ago; the US FS should have cancelled then if the gap could not be bridged.”

Novo Power has less than two years remaining on its current PPAs. “At this point we need resolution on our PPAs so that we can move forward, invest and maintain the critical employee base that we have today,” Worsley says. “We will support whatever comes in the future but our future needs certainty now.”

Funding for forest health and forest fire prevention programs and contracts is included the Biden administration infrastructure bill that is still under debate.

RELATED ARTICLES

NEWLIFE GAINS FULL PRODUCTION

 

Latest News

Carroll Is COO At Swiss Krono

Swiss Krono Group appointed Steve Carroll as its COO and Technical Director for U.S. operations at Barnwell, SC. Carroll comes to Swiss Krono from Arauco North America where he most recently served as director of the Grayling, Mich. operations. He brings to Swiss Krono more than 30 years of experience in…

CPA, APA Leaders Size Up Situation

Leadership from two of the major primary panel production associations provided 2022 year-end reports, while also looking ahead to 2023 and both pointed to economic issues moving forward. “This year (2022) was more ‘back to normal,’ as the COVID pandemic was mostly in the rearview mirror. There were…

Con-Vey Names Goebel Vice President

Con-Vey LLC, a North American-based manufacturer of automated material handling equipment for engineered wood products, is pleased to announce the promotion of Jeremy Goebel to Vice President. With over 10 years of experience at Con-Vey, Goebel brings a wealth of industry knowledge and leadership to…

Brett Helped To Pave Way For Panel World

Alan Douglas Brett, who in the latter half of his career led the international advertising sales growth of Panel World magazine, and whose vigorous life included professional motor cycle speedway racing as a young man and a long stint as sales manager with the Daily Telegraph in London, died January…

Find Us On Social

Newsletter

The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.

Subscribe/Renew

Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!

CalPlant I Regroups, Sale Is Possible

CalPlant I Regroups, Sale Is Possible

CalPlant I Regroups, Sale Is Possible

 

CalPlant I, LLC, which took 25 years to develop and build a rice straw-based medium density fiberboard plant and produce its first board late last year in Willows, Calif., has voluntarily filed for Chapter 11 bankruptcy protection and intends to conduct a court-supervised sale process.

The company has entered into a Plan Support Agreement (PSA) with its senior bondholders, which provides for a comprehensive financial restructuring of the company’s debt and the investment resources to complete the commissioning of the manufacturing facility en route to the sale of the operation.

The company states it will continue to operate without disruption to its vendors, customers or employees, and will have sufficient liquidity to meet its financial obligations throughout the restructuring process.

Jeffrey Wagner, Cal­Plant Executive Chairman, comments, “The road to fully commissioning our plant has not been smooth. We started commissioning our facility in early March 2020, then the pandemic hit. Suddenly, the usual challenges and delays associated with a startup were compounded with navigating a startup using first-of-its-kind technology during a global pandemic. Still, our team remained dedicated, resilient and ready to pivot to continue our momentum towards completion.”

CalPlant is located in the Sacramento Valley, an area estimated to have an annual quantity of more than 1.5 million tons in rice straw waste. Once operating at full capacity, the company expects to process around 280,000 tons of otherwise non-recyclable rice straw from its surrounding regions per year to produce 150MMSF of MDF product. The pioneering operation was founded upon eliminating the need for post-harvest flood­ing, thus reducing water usage and methane emissions, en route to becoming the world’s first commercial-scale manufacturer of no-added-formaldehyde, rice straw-based MDF, a product line which it eventually started calling “Eureka.”

“We are confident that leveraging the benefits of the Chapter 11 process will allow us to emerge with a stronger financial structure that enables us to continue leading the manufacturing industry with innovative sustainable MDF,” Wagner adds.

The company states it has secured commitments for up to $30.1 million in Debtor-in-Possession (DIP) financing from certain of the company’s senior bondholders to support the business during the Chapter 11 process. Subject to court approval, CalPlant estimates that substantially all trade vendors who will have an ongoing business relationship with the company will be paid for goods and services in the normal course of business without interruption.

CalPlant expects that the deadline to submit qualified binding bids will be established at a later date pursuant to bidding and sale procedures to be approved by the court.

CalPlant and its predecessor company, CalAg, LLC, spent many years and millions of dollars researching, developing and patenting a process to make high-quality MDF using annually renewable rice straw as the feedstock, the disposal of which had posed environmental issues in California for decades. The post-harvest rice straw was burned at a nominal cost to farmers until California banned the burning due to air quality concerns, leading to greater expense for farmers to dispose of the straw.

CalPlant secured it raw material needs by executing long-term fixed price rice straw supply contracts.

The project went through a series of unsuccessful efforts to pull together funding, and then in June 2017 closed the deal with $92 million in equity from a small consortium of investors and $225 million in tax-exempt bonds issued via the California Pollution Control Financing Authority and subsequently sold to qualified institutional investors.

Following a separation with the initial general contractor, CalPlant began coordinating with machinery manufacturer Siempelkamp to complete construction of the plant, including the installation of a ContiRoll continuous press 10 ft. x 117 ft. However, in addition to scheduling issues caused by the pandemic, the plant ran into issues in the refiner system, according to a bankruptcy declaration by the company. The mill reportedly continues to wrestle with some front end issues but the remainder of the plant is reportedly running well, while areas of operation continue to be optimized or modified. “Plant acceptance” may be achiev­ed early next year, but full operating capacity is not anticipated for a while.

A source close to the operation reports the mill produced 3MMSF (3⁄4 in. basis) in September but struggled with uptime, averaging 40-45%. As of early October it had 700 truckloads in the market and the board is said to be performing well in the applications in which it is being used. Reaching 8MMSF month­ly at year end is a possibility and could entice an investor or industry company to come in and ramp it up to its full potential. The inventory of straw on the yard is said to be substantial.

A May monthly bondholder report pointed to lack of available liquidity and increased expenses such as with MDI re­sin. The project had taken on additional funding beyond the original financing. Reports of non-payment of scheduled interest began surfacing late last year.

RELATED ARTICLES

CALPLANT I GEARS UP FOR FIRST BOARD

CALPLANT I NEARS THE FINISH (OR STARTING) LINE

CALAG RICE STRAW MDF PLANT

Latest News

Carroll Is COO At Swiss Krono

Swiss Krono Group appointed Steve Carroll as its COO and Technical Director for U.S. operations at Barnwell, SC. Carroll comes to Swiss Krono from Arauco North America where he most recently served as director of the Grayling, Mich. operations. He brings to Swiss Krono more than 30 years of experience in…

CPA, APA Leaders Size Up Situation

Leadership from two of the major primary panel production associations provided 2022 year-end reports, while also looking ahead to 2023 and both pointed to economic issues moving forward. “This year (2022) was more ‘back to normal,’ as the COVID pandemic was mostly in the rearview mirror. There were…

Con-Vey Names Goebel Vice President

Con-Vey LLC, a North American-based manufacturer of automated material handling equipment for engineered wood products, is pleased to announce the promotion of Jeremy Goebel to Vice President. With over 10 years of experience at Con-Vey, Goebel brings a wealth of industry knowledge and leadership to…

Brett Helped To Pave Way For Panel World

Alan Douglas Brett, who in the latter half of his career led the international advertising sales growth of Panel World magazine, and whose vigorous life included professional motor cycle speedway racing as a young man and a long stint as sales manager with the Daily Telegraph in London, died January…

Find Us On Social

Newsletter

The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.

Subscribe/Renew

Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!

NewLife Gains Full Production

NewLife Gains Full Production

NewLife Forest Restoration has ramped up production at its new engineered wood products plant in Bellemont, Ariz., while also increasing forest restoration work in service of its 4 Forest Restoration Initiative (4FRI) Phase 1 Forest Service stewardship contract that seeks to thin and treat more than 300,000 acres at risk of wildfire on the Kaibab, Coconino, Apache-Sitgreaves and Tonto national forests.

At Bellemont, the operation is currently processing low-grade cants into 1 in. lumber that’s chopped and fingerjointed and a portion is edge-glued and/or face-glued, while using structural and non-structural glues depending on the application, according to Ted Dergousoff, CEO of NewLife. They are presently using cants because the sawmill with log breakdown hasn’t been built yet.

The EWP plant is part of a much larger 425,000 sq. ft. formerly vacated facility (10 acres under one roof) that NewLife purchased in 2020. It is divided into three sections—one for the currently operating EWP plant, and the other two for the sawmill and planer mill to be built. Dry kilns will also be located on the grounds. The operation has rail access and is situated on I-40, a major truck route.

NewLife has designed the scale of the plant to accommodate upgrading products, not just from its own mills, but also from other operators in the area. In this way, many parties can work together on forest restoration, enabling the industry to scale up in the state.

Dergousoff expects NewLife’s multiple operations to be fully built by the end of 2022. The sawmill will have an annual production capacity of 120MMBF, 100% ponderosa pine, with emphasis on boards (both solid and engineered) and low-grade specialty solid items.

The sawmill will handle a mix of large and small logs, and its plan to maximize value will help offset costs incurred processing and handling the large amounts of biomass the contract is generating.

Awarded the Phase 1 contract in 2013, NewLife had struggled initially considering the state’s timber infrastructure had almost disappeared following federal timber sale cutbacks in the 1980s and ‘90s, and the company was starting from scratch in setting up harvesting and processing capacity. New Life had initially planned a greenfield sawmill at a site in Williams, Ariz., but switched to Bellemont after a large former paper products finishing plant industrial building became available.

The sawmill will handle a mix of large and small logs, and its plan to maximize value will help offset costs incurred processing and handling the large amounts of biomass the contract is generating.

NewLife has tripled the size of its forest restoration operations in light of these developments with three forest thinning crews now active and a fourth crew mobilizing. Each crew is capable of restoring 2,000-2,500 acres per year. NewLife plans to gradually increase to 25,000-plus acres of restoration capacity over the next 18-24 months as it completes installations at Bellemonte.

NewLife and its partners are operating a total of nine harvesting crews in Arizona with a combined capacity of 20,000 acres per year. In 2023, they will ramp up to more than 17 forest restoration crews with more than 40,000 acres per year of restoration capacity. The company and its partners plan to hire more than 300 skilled workers across manufacturing and forest harvesting in the next 12 months.

The 4FRI is a groundbreaking forest health effort seeking to reduce wildfire risk on 2.4 million acres across four Arizona national forests. A larger Phase 2 contract covering the restoration of up to 600,000 acres over 20 years is expected to be awarded soon. NewLife is reportedly one of several entities interested in gaining the contract.

“I do think that the only way that forest restoration can work is with a vertically integrated process,” Dergousoff says, emphasizing NewLife’s capabilities “to make it all work in unison with a goal to maximize value.”

 

Latest News

Egger Starts Up Saturation Line

Wood-based materials manufacturer, Egger Wood Products, recently completed construction of a $22 million decorative paper saturation line at its Lexington, NC facility. The new line will infuse decorative papers with resin adhesive necessary for…

Acres Partners With Forisk

Acres, a data-driven land research platform that supports fast, informed decision making, is partnering with Forisk Consulting, a leader in analyzing timber markets and wood baskets, to visualize timber data for both companies’ clients. This collaboration…

Velarde Joins AFRY Team

AFRY Management Consulting has announced that Guillermo Velarde will lead the Wood Products and Surfaces Team in North America. Guillermo has been named a Principal Consultant at the AFRY’s New York office. He has more than 15 years of…

Find Us On Social

Newsletter

The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.

Subscribe/Renew

Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!

Labor, Materials Issues Cause Project Delays

Labor, Materials Issues Cause Project Delays

The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.

In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.

The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.

Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.

Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.

According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.

 

Latest News

Roseburg Makes Major Decision

Roseburg Forest Products, which announced in April a $700 million investment over the next four years to expand operations in southern Oregon, including a $450 million MDF plant in Dillard, Ore., has selected Siempelkamp as the primary supplier of the MDF plant, including a 10 ft. x 42.1 m ContiRoll continuous press. The companies noted that in 1969 Siempelkamp supplied Roseburg Lumber with its very first composite panel press line…

APA Board Adds Beers As Trustee

APA, The Engineered Wood Assn. Board of Trustees has added John Beers III as its newest member. He joins the APA Board of Trustees, filling the position vacated by Andy Konieczka’s resignation and move to a new role within Georgia-Pacific. Beers currently serves as the president of the structural panels business at Georgia-Pacific…

J.M. Huber Corp. Receives Management Honor

J.M. Huber Corp. (Huber) has proudly announced it has been selected as a 2023 U.S. Best Managed Company Gold Standard honoree. Sponsored by Deloitte Private and The Wall Street Journal, the program recognizes outstanding U.S. private companies and the achievements of their management teams. The 2023 designees are U.S. private companies that have…

Dieffenbacher Names New Energy Unit Director

Wolfgang Lashofer has been appointed as the new Managing Director of Dieffenbacher Energy GmbH, which was formed at the beginning of the year following the acquisition of BERTSCHenergy, based in Bludenz, Western Austria. As Managing Director of Dieffenbacher Energy, Lashofer takes over the management of the newly established Energy Business Unit…

Find Us On Social

Newsletter

The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.

Subscribe/Renew

Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!

Roseburg To Shut Down Dillard P’board

Roseburg To Shut Down Dillard P’board

Roseburg Forest Products (RFP) announced on August 25, 2021 that it will shut down its particleboard plant in Dillard, Ore. The plant has been in operation since 1965, and will continue running as the plant prepares for shut down in the next 60 days.

The move to close was part of a restructuring within the company. It comes after an announcement by RFP of a multi-million dollar investment in new technology at its other Western manufacturing facilities.

“The decision to stop production at a facility is never easy, and these transitions have significant impact on the people involved,” Roseburg senior vice president of operations Jake Elston says. “We have already begun working with our current team members on this upcoming transition to identify other opportunities within the organization.”

According to news reports, RFP will offer the 179 employees opportunities at other Oregon facilities after the plant is shuttered—with the goal to offer uninterrupted local employment to as many team members as possible. The company moved its corporate headquarters from Dillard to Springfield, Ore. in 2016, but RFP still operates sawmill and plywood plants in Dillard, as well as a regional administrative office and a truck shop, plus a wood-to-energy plant. RFP also operates plywood and engineered wood plants in Riddle.

RELATED ARTICLES

PRODUCERS ANNOUNCE PERSONNEL CHANGES

NEW STRATEGIC MARKETING MANAGER FOR ROSEBURG

ROSEBURG GETS CHESTER ROLLING

 

Latest News

Daniels, Pannell Join PotlatchDeltic

PotlatchDeltic Corp. has announced that Ryan Daniels and Bobby Pannell have joined the Wood Products division, with Daniels serving as Director of Operations, responsible for leading the manufacturing teams at the six lumber facilities and the St. Maries plywood mill, and Pannell serving as…

BE&E Purchases Conveying, Fabrication From BID

BID Group and Biomass Engineering & Equipment (BE&E) announced a strategic supply and outsourcing partnership, in which BE&E will acquire the Vibrapro brand and manufacturing operations located in Boise, Id., and the BID Group fabrication plant in Greenville, Ky…

Egger Starts Up Saturation Line

Wood-based materials manufacturer, Egger Wood Products, recently completed construction of a $22 million decorative paper saturation line at its Lexington, NC facility. The new line will infuse decorative papers with resin adhesive necessary for…

Find Us On Social

Newsletter

The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.

Subscribe/Renew

Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!

Producers Announce Personnel Changes

Producers Announce Personnel Changes

Ashlee Cribb Succeeds Tom Temple At Potlatch

PotlatchDeltic Corp. has appointed Ashlee Cribb as Vice President, Wood Products. She succeeds Tom Temple, who is retiring in October after serving in this role since 2009.

“We are thrilled to welcome Ashlee,” comments Eric Cremers, PotlatchDeltic President and CEO. “Ashlee brings extensive knowledge and a strong track record with over 30 years of industry experience including positions at Georgia-Pacific LLC and Roseburg Forest Products.”

Most recently Cribb served as the senior vice president, chief commercial officer at Roseburg Forest Products based in Springfield, Ore., and prior to that held leadership roles in Roseburg’s Structural Products business. She has an MBA from Washington University, St. Louis, and earned her chemical engineering undergraduate degree at the Georgia Institute of Technology.

“I am looking forward to engaging with the team and continuing a strong commitment to the core values of the company, including excellence in safety,” Cribb says. “The PotlatchDeltic mills are well positioned and I am excited to execute on continued growth and operational excellence to deliver value for our customers, shareholders and communities.”

Doug Asano Steps Up At Roseburg As New Senior VP—Sales & Marketing

Roseburg Forest Products has named Doug Asano as Senior Vice President—Sales and Marketing. He replaces former SVP Ashlee Cribb; Asano transitions from his previous role as director of sales excellence.

“We wish Ashlee all the best in her new opportunity, and we are excited to have someone of Doug’s caliber, scope and experience available to step in immediately,” Roseburg President and CEO Grady Mulbery says. “It’s a reflection of the bench strength we have built as a company over the past several years. We anticipate a transition that allows us to move forward smoothly.”

Asano joined Roseburg in August 2020 after serving as a vice president for nine years with Huber Engineered Wood. At Huber, he brought innovation and transition to national accounts, sales and marketing, all of which fit with his new position at Roseburg. His new role will encompass the entire Commercial Team, including Sales, Distribution, Marketing, and Supply Chain and Logistics.

RELATED ARTICLES

ROSEBURG TO SHUT DOWN DILLARD P’BOARD

DAVID SMITH SERVES AS CPA CHAIRMAN, ’21 BOARD ANNOUNCED

NEW STRATEGIC MARKETING MANAGER FOR ROSEBURG

PELICE DRAWS POWERFUL SPEAKERS IN ATLANTA

ROSEBURG GETS CHESTER ROLLING

Latest News

Carroll Is COO At Swiss Krono

Swiss Krono Group appointed Steve Carroll as its COO and Technical Director for U.S. operations at Barnwell, SC. Carroll comes to Swiss Krono from Arauco North America where he most recently served as director of the Grayling, Mich. operations. He brings to Swiss Krono more than 30 years of experience in…

CPA, APA Leaders Size Up Situation

Leadership from two of the major primary panel production associations provided 2022 year-end reports, while also looking ahead to 2023 and both pointed to economic issues moving forward. “This year (2022) was more ‘back to normal,’ as the COVID pandemic was mostly in the rearview mirror. There were…

Con-Vey Names Goebel Vice President

Con-Vey LLC, a North American-based manufacturer of automated material handling equipment for engineered wood products, is pleased to announce the promotion of Jeremy Goebel to Vice President. With over 10 years of experience at Con-Vey, Goebel brings a wealth of industry knowledge and leadership to…

Brett Helped To Pave Way For Panel World

Alan Douglas Brett, who in the latter half of his career led the international advertising sales growth of Panel World magazine, and whose vigorous life included professional motor cycle speedway racing as a young man and a long stint as sales manager with the Daily Telegraph in London, died January…

Find Us On Social

Newsletter

The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.

Subscribe/Renew

Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.

Advertise

Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!