Mercer International Inc. and its subsidiary Mercer Mass Timber, a manufacturer of timber building materials, completed the acquisition of Structurlam Mass Timber Corp. and its subsidiaries in mid-June. Mercer Mass Timber immediately takes possession and continues the operation of Structurlam’s manufacturing facilities, which will now operate under the Mercer Mass Timber brand, including a new production facility in Conway, Ark. and in Penticton, British Columbia, Can.
At the end of May, Mercer International received Bankruptcy Court approval of the acquisition for $81.1 million. Structurlam had filed for bankruptcy earlier this year.
The Conway facility is a modern, state-of-the-art manufacturing facility that was built in 2021 and has an annual capacity of approximately 75,000 m3; can produce both glued laminated timber (glulam) and cross-laminated timber (CLT); includes more than 280,000 sq. ft. of manufacturing space; and is strategically located in the Southern U.S. in proximity to growing construction markets and with access to a large and high-quality regional wood basket.
The purchase also include three facilities located in British Columbia with a combined annual capacity of 40,000 m3 of glulam and CLT.
These assets complement Mercer’s existing Mercer Mass Timber facility in Spokane Valley, Wash.
“We are thrilled to welcome Structurlam into the Mercer Mass Timber fold,” says Brian Merwin, Senior Vice President of Mercer Mass Timber. “This acquisition will allow us to offer our customers a wider range of mass timber products, and to better support their projects with the addition of more cross laminated timber (CLT) capacity and glulam production capabilities. Our goal is to become a one-stop shop for all mass timber needs. The additional manufacturing facilities that the Structurlam acquisition brings will enable us to create greater efficiencies.”
A local paper in mid-June reported that the Conway facility had resumed production and will increase its pace as the order file heats up.
RELATED ARTICLES
STRUCTURLAM FILES FOR BANKRUPTCY, MAY SELL TO MERCER INTERNATIONAL
Latest News
Fletcher Building Orders Fine OSB Plant
New Zealand’s Fletcher Building Ltd. has ordered a complete plant for the production of Fine OSB from German machine manufacturer Dieffenbacher. The plant will be built at Fletcher Building’s Laminex site in Taupo, in the center of the country’s North Island. The new plant will include Dieffenbacher new belt dryer. The belt dryer is one example of how Dieffenbacher…
Uniboard Modernization On Track At Val-d’Or
Uniboard reports its $350 million particleboard plant modernization program is going as planned at Val-d’Or, Quebec; originally announced in June 2022, this is the third phase of its modernization for its particleboard and TFL mill. More than $100 million was invested in Phase 1 and Phase 2, which were…
Jim Herold Retires From Rainier Veneer
Rainier Veneer, Inc., Spanaway, Wash., announced that Plant Manager Jim Herold retired the first of June after 25 years as manager. Previously Herold worked at Roseburg Forest Products where he was plant manager of the Dillard plywood mill. He began his career at RFP after graduating from Oregon State University in 1974…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!