Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
RoyOMartin Adds Natalie Monroe To Executive Leadership Team
RoyOMartin has named Natalie Martin Monroe Vice President of Environmental, Safety, and Sustainability Operations. She will also serve as a member of the Strategic Action Leadership Team (SALT) and the Corporate Secretary for the Martin Sustainable Resources (MSR) Board of Directors…
Softwood Board, FS Announce Mass Timber Awards
The Softwood Lumber Board (SLB) and USDA Forest Service recently awarded $2 million total to six projects that highlight innovative architectural design and mass timber’s significant role in carbon reduction. According to SLB officials, lessons learned from each project will be shared with the construction community to help support future projects, including cost analyses, life cycle assessments and other research results…
Pacific Woodtech Acquires LP EWP Division
Burlington, Wash.-based Pacific Woodtech announced the acquisition of Louisiana-Pacific Corp.’s EWP (I-Joist and LVL) division for $210 million. The acquisition includes LP laminated veneer lumber and I-Joist manufacturing facilities in…
Arauco NA Expands TFL Operations
Arauco has announced that it will invest $20 million to expand its thermally fused lamination (TFL) operations at its state-of-the-art particleboard mill in Grayling, Mich. The new lamination line will be Arauco’s third TFL line at Grayling and will increase the…
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!