Labor, Materials Issues Cause Project Delays
The same labor availability issues that have plagued forest products manufacturers since the COVID pandemic began are also plaguing builders as the economy seeks to rebound. According to a survey of more than 2,000 construction companies, both hourly and salaried employees are currently very hard to find—a sentiment shared by many employers.
In an August survey, the trade group Associated General Contractors of America (AGCA) surveyed more than 2,100 construction firms around the country and found 91% were having trouble filling construction trade craft positions, while almost as many (87%) said salaried employees were hard to find as well.
The situation is ongoing for builders who have already been beset by materials price increases and availability in addition to labor issues since the COVID pandemic began. According to the survey, 88% of firms are experiencing project delays.
Three-quarters of builders cite longer lead times-material shortages for project delays, 61% cite labor shortages for and 57% said delivery delays compounded project problems.
Labor and materials issues surrounding the construction industry have broader implications since resulting delays act as a drag on the U.S. housing market and plans for large federal infrastructure projects.
According to the federal Bureau of Labor Statistics’ Job Openings and Labor Turnover Survey (JOLTS) for July, the number of unfilled construction positions is going down slowly, but 321,000 construction industry jobs remain unfilled.
Latest News
FLAMEX Names New President
FLAMEX Inc. announced Tony Thomas as its new President, succeeding Allen Wagoner after 13 years at that post. Thomas has been with the company for almost 32 years and has been serving as Vice President. Ed Pridgen assumes the role as Vice President in addition to his position as MINFOG Product Manager…
GP Announces Multi-Million Dollar Projects At Clarendon OSB
Georgia-Pacific recently announced a $20 million addition to its oriented strandboard (OSB) facility in Alcolu, South Carolina. The major scope of the project will be to add a third strander to the behemoth facility, which will increase the annual output of…
Egger Plans Third TFL Line
Egger Wood Products will invest $20 million for an additional thermally fused laminate (TFL) production line at the company’s sole U.S. location in Lexington, NC. The company’s Supervisory Board announced the investment, part of completion for Phase I work at the site, after visiting the U.S. plant for its…
Peak Renewables Hires Scott Bax
Peak Renewables Ltd., an emerging, innovative, opportunity-driven company focused on growing the forest economy with sustainably sourced and renewable energy products, is pleased to announce that Scott Bax has been appointed as Chief Executive Officer, effective December 20, 2021...
Find Us On Social
Newsletter
The monthly Panel World Industry Newsletter reaches over 3,000 who represent primary panel production operations.
Subscribe/Renew
Panel World is delivered six times per year to North American and international professionals, who represent primary panel production operations. Subscriptions are FREE to qualified individuals.
Advertise
Complete the online form so we can direct you to the appropriate Sales Representative. Contact us today!